TDI

Client: FLUOR / BASF – Ludwigshafen in Germany
Market: Process / EPC
Scope: Piping pre-fab including painting, piping & equipment erection, electrical and steam tracing, insulation, scaffolding and fabrication of column internals
Key figures: Contract size: Below €300M (confidential)
Major dates:
- November 2013: contract signed
- February 2015: transition from unit rate to time & material
- November 2015: commissioning
- June 2016: installation of insulation boxes for valves and flanges and completion of all remaining works
Key-features:
- The new plant is the first facility in the world, which is able to produce 300,000 tons per year in only one single-stranded production line
- Hertel achieved more than 3.0 million hours LTI-free
- The manpower load was at the highest in week 12 with a total of approximately 1,423 personnel (including overhead)